To start, a temporary scaffolding tin roof was placed over the property as the electrical and gas services were in the garage. Once the temporary roof was complete, the existing roof tiles were removed and placed to one side for using again once our construction consultants completed the new roof. The existing rafters followed opening the working area.
To take the brickwork up to the 1st floor, G2 had to excavate two padstone foundations for the steelwork to be based upon and fixed to. Once excavated and the concrete set, a goalpost steel frame was installed, providing the based for our front elevation brickwork to sit on. Our brickwork then followed suit, with a new front window for which will be a new family bathroom.
ONGOING PROJECT, rear underway
Click here to view the project
Read less