Project started in Nov 22 and took 12 months to complete and consisted of 5 bathrooms, 1 WC, 5 bedrooms, walk in wardrobe, new very large kitchen/dining, lounge, office, dining room, a double-sided fire, hallway, garage extension, utility, new roofs, complete rear and side landscaped garden with 250m2 porcelain tiles and retaining wall. From the start we encountered a few issues that we had to overcome. One example is that we uncovered that the first floor was not built using traditional wooden joists, but had interconnecting large concrete slabs throughout, which meant recalculating demolition, support and structural steel plans. The end result as you can see from the images is a quality delivered project to amazing clients, Sir Mike and Anne Higgins that reflect the build in their 5 star client reference to us. https://vimeo.com/910780719?share=copy